Armory Avenue Lane Closures
In order to install a sanitary force main for the Urbana Champaign Sanitary District, Stark Excavating will be closing lanes of Armory Avenue between First Street and Fourth Street. Lane closures began on Wednesday, June 3, 2015, and will continue through Friday, June 19, 2015. The installation is a moving operation and the lane closures […]
2015 CONCRETE STREET MAINTENANCE PROJECT – HOLLYCREST DRIVE
As part of the City’s 2015 Concrete Street Maintenance Project, the pavement on Hollycrest Drive from John Street to Ola Drive is being rehabilitated. The City’s contractor for the project, Stark Excavating, will continue working; weather permitting, Thursday, June 4, 2015. Hollycrest Drive will temporarily be a one lane, one-way street South Bound from John […]
2015 CONCRETE STREET MAINTENANCE PROJECT – HOLLYCREST DRIVE
2015 CONCRETE STREET MAINTENANCE PROJECT – HOLLYCREST DRIVE Champaign – As part of the City’s 2015 Concrete Street Maintenance Project, the pavement on Hollycrest Drive from Ola Drive to John Street will be rehabilitated. The City’s contractor for the project, Stark Excavating, will begin work; weather permitting, Thursday, May 7, 2015. Hollycrest Drive will temporarily […]
2015 CONCRETE STREET MAINTENANCE PROJECT – HOLIDAY DRIVE
2015 CONCRETE STREET MAINTENANCE PROJECT – HOLIDAY DRIVE Champaign – As part of the City’s 2015 Concrete Street Maintenance Project, the pavement on Holiday Drive from William Street to Frank Drive will be rehabilitated. The City’s contractor for the project, Stark Excavating, will begin work; weather permitting, Monday, May 4, 2015. Holiday Drive will temporarily […]
Windsor Road Project
The State of Illinois awarded a contract to Stark Excavating to widen the approaches to the bridge on Windsor Road over I-57. Construction began on April 1. The road will be open to traffic on August 15, 2014. Construction will be completed by October 15, 2014. Stark is installing storm sewers on the east of […]
Robinson Court Detention
Rain has slowed the construction of the Robinson Court Detention Basin. Stark Excavating has completed approximately 75% of the basin construction. With good weather, Stark will quickly get back on schedule and complete the project on time. The project is scheduled to be completed by the end of this year.
Fourth Street
Stark Excavating is nearing project completion on the Fourth Street Improvement Project. Stark Excavating has completed the paving of Gerty Drive east of Fourth Street. They continue to work on the landscaping.
Windsor Road Project
Stark Excavating was awarded the City project that would widen the approaches to the bridge on Windsor Road over I-57. Construction began on April 1 and will be complete on October 15, 2014. Windsor Road will be open for traffic on August 15, 2014. Stark has completed construction of the retaining walls on the west […]
Washington Street Drainage Improvements (Robeson Court Detention Basin)
The City of Champaign has awarded a contract to Stark Excavating for the construction of the Washington Street drainage improvements. This project will consist of constructing a new detention basin and amenities along with an upgraded storm sewer system at the intersection of Washington and Russell Street. The basin improvements will be complete before the […]
Windsor Road Project Update
Stark Excavating is widening the approaches to the bridge on Windsor Road over I-57. Construction began on April 1 and will be complete on October 15, 2014. It’s required that the road be open for traffic on August 15, 2014. Stark is currently constructing the foundation for the retaining walls. Due to the existing development, […]