i3 Broadband Fiberoptic Construction Project – Mattis/Draper/University/John

The City of Champaign shares the following information on behalf of i3 Broadband: i3 Broadband will begin installation of fiberoptic utility in an area between Mattis and Draper (from west to east) and between University and John (from north to south). The construction process will continue for 6-8 weeks from first seeing utility flags to […]


University Avenue Lane Closure – REVISED

In order to facilitate demolition at 306 E. University Avenue, Stark Excavating will close one westbound lane of University Avenue between Third Street and Fourth Street. The closure will begin on Monday, September 25, and will reopen on Thursday, October 5, 2023. During the closure, westbound traffic will be reduced to one lane in the […]


Country Fair Drive Lane Closure

In order to perform storm sewer repairs, SNC Construction will be closing the northbound right turn lane of Country Fair Drive onto University Avenue. All travel at the intersection will remain open to traffic and normal traffic patterns will be maintained. Work is scheduled to begin at 7 a.m. on Tuesday, September 26, and is […]


University Avenue Lane Closure (between Fourth Street and Third Street)

In order to facilitate demolition at 306 E University Avenue, Stark Excavating will close one westbound lane of University Avenue between Fourth Street and Third Street.  The closure will begin on Monday, September 25, and will reopen on Friday, September 29, 2023.  During the closure, westbound traffic will be reduced to one lane in the […]


University Avenue Lane Closure and Walnut Street Lane Closure

In order to complete a sanitary sewer lining project, Hoerr Construction will be closing a westbound lane of University Avenue between Walnut Street and Market Street and also a northbound lane of Walnut Street at Taylor Street.  Work is scheduled to begin at 5 a.m. on Tuesday, September 12, 2023, and is planned to be […]


University Avenue Lane Closure (between First Street and Chester Street)

In order to perform storm sewer lining, Hoerr Construction will be closing the right lane of westbound University between First Street and Chester Street. During this time, University Avenue westbound will be reduced to a single lane thru a short construction work zone. Chester Street will also be reduced lane widths thru a work zone […]


University Avenue Lane Closure (between Neil Street and Market Street)

In order to complete a sign installation at 17 E. University Avenue, Bendsen Signs and Graphics, Inc. will close a lane of University Avenue between Neil Street and Market Street and a lane of Walnut Street between Logan Street and University Avenue. The lane closures will begin on Thursday, July 13, 2023, and will be […]


University Avenue Lane Closures

University Avenue Lane Closures (between Chestnut Street and First Street) CHAMPAIGN – Starting Tuesday June 6, 2023, Pole Painting Plus will be in town repainting the traffic signal at the intersection of University Avenue and Chestnut Street. They will then move on to repaint the streetlight poles between Chestnut Street and First Street along University […]


Walnut Street Lane Closure (between Taylor Street and University Avenue)

In order to complete material delivery at 114 N. Walnut, C-U HVAC, Inc. will close one northbound lane of Walnut Street between Taylor Street and University Avenue. During the closure, northbound traffic will be reduced to one lane in the area. The closure will occur between the hours of 7 a.m. and 11 a.m. on […]


University Avenue Lane Closure (between Chestnut Street and First Street)

In order to repair a sanitary sewer service, Lanz Underground will close one eastbound lane of University Avenue between Chestnut Street and First Street. Eastbound traffic will be reduced to one lane in this area. When possible, the lane will be reopened to traffic overnight and throughout the weekend.  The closure will begin on Monday, […]