Third Avenue Road Closure (Between Springfield Avenue and Healey Street)

In order to place a crane and complete material delivery at 512 S. Third Street, Custom Service Crane will be closing Third Street between Springfield Avenue and Healey Street. The closure will occur on Friday, July 19, 2019, between the hours of 7 a.m. and 7 p.m. During the closure, through traffic will not be […]


Hickory Street Road Closure (South of Howard Drive)

As part of the Boneyard Creek North Branch Improvements, Feutz Contractors will be replacing the Boneyard Creek culvert under Hickory Street south of Howard Drive. Hickory Street will be closed south of Howard Drive for this work. Access to residences on Leichner Drive and Howard Drive will be maintained via a temporary detour north of […]


Third Street Road Closure – Rescheduled (between Springfield Avenue and Healey Street)

In order to place a crane and complete material delivery at 512 S. Third Street, Custom Service Crane will be closing Third Street between Springfield Avenue and Healey Street. The closure will now occur on Monday, July 8, 2019, between the hours of 7 a.m. and 7 p.m. During the closure, through traffic will not […]


John Street Road Closure (between Locust Street and Oak Street)

In order to complete an emergency sanitary sewer repair at 33 E. John Street, Duce Construction will immediately be closing John Street west of Locust Street. The closure will begin today, Tuesday, July 2, and will reopen on Tuesday, July 9, 2019. Access to properties west of Locust will be maintained via Oak Street.


Sixth Street Road Closure (between Green Street and John Street)

In order to complete utility connections at 708 S. Sixth Street, Core Spaces and J H Findorff will be closing Sixth Street between Green Street and John Street. The following closure has been scheduled: Monday, July 8 through Friday, July 12, 2019 During the closure, Sixth Street will be closed to through traffic between Green […]


Prospect Avenue Road Closure (from Windsor Road to Curtis Road)

As part of the South Prospect Avenue construction project, the City’s contractor plans to begin Stage II of construction on Monday, July 1, 2019. This stage is expected to last two months depending on weather. Stage II construction will close Prospect Avenue from just south of Bloomfield Court to approximately 500 feet north of Pittsfield […]


Third Street Road Closure – Rescheduled

In order to place a crane and complete material delivery at 512 S. Third Street, Custom Service Crane will be closing Third Street between Springfield Avenue and Healey Street. The closure will now occur on Tuesday, July 2, 2019, between the hours of 7 a.m. and 7 p.m. During the closure, through traffic will not […]


Third Street Road Closure (Between Springfield Avenue and Healey Street)

In order to place a crane and complete material delivery at 512 S. Third Street, Custom Service Crane will be closing Third Street between Springfield Avenue and Healey Street. The closure will occur on Friday, June 28, 2019, between the hours of 7 a.m. and 7 p.m. During the closure, through traffic will not be […]


West Washington Street Drainage Improvements – Phase III (Church Street Lane Closure)

As part of Phase III West Washington Street Drainage Improvements, Stark Excavating will close the north lane of Church Street between James Street and Edwin Street.  Westbound traffic on Church Street will be directed into the south lane through the construction zone. The closures listed below will also be a part of the Church Street […]


John Street Road Closure – Extended

In order to complete utility connections and patch pavement at 104 E. John Street, Sub 4 Development and Mid Illinois Concrete will be closing John Street between First Street and Second Street. The closure began Monday, June 3, and will now reopen on Monday, June 17, 2019. During the closure, through traffic will not be […]