Surveying Set to Begin in Garden Hills
Topographic surveying in the Garden Hills Neighborhood will begin on October 25, 2021. This work is part of the planned drainage and lighting improvements in the Garden Hills Neighborhood that will be implemented over the next few years. The City’s consultant engineer (Clark Dietz) will perform the topographic surveying in the areas highlighted on the […]
Phase 2 – West Washington Street Drainage Improvements
The City and the West Washington Street Steering Committee hosted an Open House meeting on January 12 to present the proposed concept plans for Phase 2 of the West Washington Street Drainage Improvements project. The project includes the construction of new stormwater detention basins along Glenn Park Drive between Mattis Avenue and Miller Avenue. Once […]
Washington Street Drainage Improvements
The City of Champaign would like to announce that on Monday, September 22, 2014, West Washington Street between Russell Street and Garfield Avenue and the intersection of Washington Street and Russell Street will be closed to traffic. This closure is necessary to reconstruct the City’s infrastructure and improve drainage at the intersection of Washington Street […]
Washington Street Drainage Improvements
Rain has slowed the earth excavation phase of the project. Stark Excavating has completed approximately 50% of the basin construction. With good weather, Stark will quickly get back to work and complete the project on time. The project is scheduled to be completed by the end of this year.
2014 Slurry Seal Project
This year’s slurry seal project has been completed. Microsurfacing Contractors LLC from Peoria, Illinois sealed 11.5 lane miles of oil and chip type streets in the northern one-third of the City. Eight (8) manholes were adjusted up to match the current roadway surface elevation. Minor drainage improvements were made to North Champaign Street to correct […]
Washington Street Drainage Improvements (Robeson Court Detention Basin)
The City of Champaign has awarded a contract to Stark Excavating for the construction of the Washington Street drainage improvements. This project will consist of constructing a new detention basin and amenities along with an upgraded storm sewer system at the intersection of Washington and Russell Street. The basin improvements will be complete before the […]