Windsor Road and Duncan Road Lane Closures
In order to perform routine storm sewer maintenance activities, National Power Rodding Corp. will have single-lane closures affecting traffic in the intersection of Duncan Road and Windsor Road. Traffic will only be affected in one single area at a time with traffic control to reroute travelers. Work is planned during the hours of 7 a.m. […]
Windsor Road and South Mattis Avenue Lane Closures
In order to perform routine storm sewer maintenance activities, National Power Rodding Corp. will have single-lane closures affecting traffic traveling on West Windsor Road and on South Mattis Avenue. Traffic will only be affected in one single area at a time with traffic control to re-route travelers. Work is planned during the hours of 7 […]
Windsor Road Lane Closures (between Prospect Avenue and Galen Drive)
In order to perform routine storm sewer maintenance activities, National Power Rodding Corp. will have single-lane closures affecting traffic traveling on Windsor Road between Prospect Avenue and Galen Drive. Traffic will only be affected in one single area at a time with traffic control to re-route travelers. Work is planned during the hours of 7 […]
Windsor Road and Mattis Avenue Lane Closures
In order to perform routine storm sewer maintenance activities, National Power Rodding Corp. will have single-lane closures affecting traffic traveling on West Windsor Road and on South Mattis Avenue. Traffic will only be affected in one single area at a time with traffic control to re-route travelers. Work is planned during the hours of 7 […]
First Street and Windsor Road Early Morning Road Work
First Street and Windsor Road Early Morning Road Work Duce Construction, the City of Champaign’s contractor for the 2021 Concrete Street Maintenance Project will begin maintenance activities on Windsor Road (between First Street and Neil Street) & First Street (between Windsor Road and St. Mary’s Road). This work will begin at 6:00 a.m. Friday, July […]
2021 Concrete Street Improvements Project (First Street from Windsor Road to Saint Mary’s Road)
As part of the City’s 2021 Concrete Street Improvements Project, the pavement on First Street from Windsor Road to Saint Mary’s Road will be patched. The City’s contractor for the project, Duce Construction, will begin work on July 13, 2021. This project is expected to be completed by August 14, 2021; however, the work is […]
2021 Concrete Street Improvements Project (Windsor Road from Neil Street to First Street)
As part of the City’s 2021 Concrete Street Improvements Project, the pavement on Windsor Road from Neil Street to First Street will be patched. The City’s contractor for the project, Duce Construction, will begin work on Tuesday, July 6, 2021. This project is expected to last eight weeks; however, the work is weather dependent and […]
Fields South Drive Road Closure (south of Windsor Road)
In order to repair pavement failures, Feutz Contractors will be closing the 2400 block of Fields South Drive just south of Windsor Road. Repair work will begin on Friday, May 21, 2021, and last two days, weather permitting.
Windsor Road Lane Closure (between Fox Drive and Windsor Place)
In order to facilitate fiber optic boring, Stark Excavating will close one eastbound lane of Windsor Road between Fox Drive and Windsor Place. The closure will occur on Monday, April 26 between the hours of 7 a.m. and 5 p.m. Eastbound traffic will be reduced to one lane in the area.
Prospect Avenue Road Closure (From Windsor Road to Harrington Drive)
In order to perform milling and paving work as part of the 2020 Annual Paving Project, Prospect Avenue from Windsor Road to Harrington Drive will be closed to all traffic on Thursday, May 28, 2020, starting at 7 a.m. Northbound motorists will be detoured to the east side on Windsor Road to Neil Street. Southbound […]