Items tagged: basin

Washington Street Drainage Improvements

Rain has slowed the earth excavation phase of the project. Stark Excavating has completed approximately 50% of the basin construction. With good weather, Stark will quickly get back to work and complete the project on time. The project is scheduled to be completed by the end of this year.


Washington Street Drainage Improvements (Robeson Court Detention Basin)

The City of Champaign has awarded a contract to Stark Excavating for the construction of the Washington Street drainage improvements. This project will consist of constructing a new detention basin and amenities along with an upgraded storm sewer system at the intersection of Washington and Russell Street. The basin improvements will be complete before the […]