2014 Concrete Street Maintenance

Fourth Street
Beniach Construction continues work on Fourth Street from Bradley Avenue to East Vine Street. The work involves pavement patching, sidewalk repairs and lawn restoration. Fourth Street is scheduled to be completed by July 31, 2014.

Phillips Drive
Beniach Construction is nearing completion on Phillips Drive from Nelson Court to the Railroad tracks. The work involves pavement replacement, sidewalk repairs, construction of ADA compliant sidewalk ramps and lawn restoration. All pavement, curb and sidewalk work should be completed by Friday July 25.