The majority of work on MCORE Project 2 & 3 wrapped up Monday, with the reopening of White Street to through traffic between Second Street and Wright Street. The newly improved corridor of White Street contains wider driving lanes, bike lanes, new landscaping, improved sidewalks, and additional lighting. The intersection of Fourth Street and White Street has also been enhanced, with a traffic signal, providing for safer crossing for all modes of transportation. Work will continue to occur on landscaping and cleanup.
Project 4 is expected to begin in Spring 2019, with more information to be shared regarding the schedule closer to construction kickoff. For additional information visit www.mcoreproject.com.