Fire Station 3 Addition Construction Update
Stronghold Construction Inc. of Monee, IL continues to make progress on the construction of the Fire Station 3 Addition project. In the past two weeks, they have poured the interior floor slab, and they have started the process of laying the exterior brick. Stronghold’s masonry subcontractor should complete the exterior brick work this week if […]
Fire Station 3 Addition Construction Update
Stronghold Construction Inc. of Monee, IL continues to make progress on the construction of the Fire Station 3 addition project. In the past two weeks, they have constructed the roof on the new addition, installed a new door and window, and demolished the old north exterior wall. Exterior brick installation has begun and should be […]