Fire Station 3 Addition Construction Update

Stronghold Construction Inc. of Monee, IL continues to make progress on the construction of the Fire Station 3 addition project.  In the past two weeks, they have constructed the roof on the new addition, installed a new door and window, and demolished the old north exterior wall. Exterior brick installation has begun and should be completed in the next couple weeks.  The project is on schedule for completion by the end of July 2015.

 