Country Fair Drive Road Closure (between Church Street and Bradley Avenue)

Country Fair Drive Road Closure
(between Church Street and Bradley Avenue)

CHAMPAIGN – As part of the City’s Spring Pavement Patching Project, Feutz Contractors will be closing Country Fair Drive between Church Street and Bradley Avenue.

The work will be done in five phases with each phase expected to last three-to-four days, weather permitting. Work begins in Phase 1 on Thursday, March 23, 2023.
• Phases 1 and 2 are between Church Street and Springer Drive.
• Phase 3 is between Springer Drive and Cone Drive
• Phase 4 is between Cone Drive and Camp Drive
• Phase 5 is between Camp Drive and Bradley Avenue

Please do not park on the street near the construction site or in areas that are posted “No Parking”. Proceed cautiously through construction zones and use alternate routes whenever possible.  The contractor will maintain access to businesses at all times during the project and will attempt to complete construction activities as soon as possible to minimize any inconvenience to businesses and residents in the areas of construction.

The City of Champaign would like to thank you for your cooperation and patience during the remainder of this construction season.

Map_Country Fair between Church and Bradley)