Progress on University Avenue from Mattis Avenue to State Street continues to move forward. Next week the contractor will continue to construct curb and a sidewalk ramp on the south side of the street. There will be intermittent lane closures throughout the construction period. However, one lane will be open at all times. Access to driveways and businesses will be open at all times. Work on University Avenue will be completed by August 16, 2013.