Staley Road Project Stage 2

Open Road Paving Company has begun work on Stage 2 (Bradley Avenue to Bloomington Road / Route 150) of the Staley Road Project. Stage 2 work items consist of milling off the old surface, patching, 2 foot wide asphalt safety shoulder, guardrail installation, pipe culvert installation, and miscellaneous ditch grading work. This stage is expected to be completed in 4 to 6 weeks. Twenty Five (25) percent of the existing pavement (2,500 tons) will be recycled and used in the new asphalt being paved on the Staley Road Project.

Javalina Construction Co. from Indianapolis, IN milling existing asphalt pavement.  7-2-12

Javalina Construction Co. from Indianapolis, IN milling existing asphalt pavement. 7-2-12

 

Trucks lined up in front of milling equipment.  7-2-12

Trucks lined up in front of milling equipment. 7-2-12