The Staley Road Project is on schedule to proceed to Stage 2 (Bradley Avenue to Bloomington Road / Route 150) on June 29. Stage 1 (Springfield Avenue / Route 10 to Bradley Avenue) will re-open to traffic while Stage 2 will be closed to traffic. Remaining Stage 1 items consist of earthwork, temporary striping, seeding, and mulching. After Stage 2 is complete, the entire length of roadway will receive the final lift of asphalt and permanent pavement striping. The contractor expects to be complete by August 25.