2024 Concrete Street Improvements Project (Park Terrace Lane)

As part of the City’s 2024 Concrete Street Improvements Project, the pavement on Park Terrace Lane from Robert Drive to Augusta Drive will be reconstructed. Stark Excavating will be the contractor for the City of Champaign and will begin work, weather permitting, on May 6, 2024.

Starting Monday, May 6, 2024, the westbound lane of Park Terrace Lane will be closed between Robert Drive and Augusta Drive. This section of Park Terrace Lane will temporarily become one-lane, one-way eastbound traffic only. Work on this project will take approximately four to six weeks. Lawn restoration will be done in the fall during the optimal growing season to allow the new sod to thrive.

Map_Park Terrace from Robert to Augusta