Holiday Drive
Stark Excavating has completed all concrete work on Holiday Drive from Frank Drive to William Street. The work consisted of removal and replacement of a large portion of the existing pavement, curb and gutter replacement and sidewalk repairs. Lawn restoration will be completed later this fall. Stark completed the work on Holiday Drive ahead of schedule.
Hollycrest Drive
Stark has completed all pavement and curb and gutter work on the northbound and southbound lanes of Hollycrest Drive, between John Street and Ola Drive. Only remaining items of work are sidewalk and sidewalk ramps. Lawn restoration will be completed later this fall. Stark is ahead of schedule for completing the project on time.
Mayfair Road
Stark began work on the north bound lane of Mayfair Road between Lincolnshire Drive and Broadmoor Drive on Monday, June 15. The project consists of removal and replacement of large portions of concrete and curb and gutter and lawn restoration. The completion date for the work on Mayfair Road is August 8, 2015. Â Lawn restoration will be completed later this fall.