On Monday, May 19, 2014, A&R Services will begin work on the Healey Street Reconstruction Project. The work will consist of storm sewer improvements, new curb and gutter, new pavement and new sidewalk. Weather permitting, the major work items will be completed by Friday, August 15, 2014.
The project limits are Healey Street from Fourth Street to Sixth Street including the intersections. This will bring the Fourth, Fifth and Sixth Street intersections of Healey Street up to campus streetscape standards. While parts of Healey Street will be closed during the project, two-way traffic will be allowed for access to driveways in the construction area.
The contractor will attempt to complete construction activities as soon as possible to minimize any inconvenience to the residents in the areas of construction.A map showing this location along with all 2014 City Engineering Division projects can be found at www.ci.champaign.il.us/pwd, click on “2014 Construction Maps”