In order to complete a sanitary sewer service connection at 75 E Armory Avenue, Mayfield Construction will be closing a lane of First Street between Armory Avenue and Gregory Drive. This work will occur in two phases:

Phase One (Monday, March 18 – Wednesday, March 20, 2013)
During working hours, two-way traffic on First Street will be reduced to one lane. Flaggers will be present to direct traffic through the area. Overnight, all lanes will be reopened.

Phase Two (Thursday, March 21 – Monday, March 25, 2013)
Two-way traffic will be maintained at all times while a narrow section of First Street will be closed for concrete patching. Appropriate traffic control will guide northbound and southbound traffic through the area with no delay.