2012 Concrete Street Maintenance

Plymouth Drive
Duce Construction has completed all of the pavement, curb and sidewalk repairs on Plymouth Drive from Harrington Drive to Devonshire Drive. A few items (punch list) of work remain. Lawn restoration will be done by September 30.

Harris Avenue
Duce Construction has completed all of the pavement patching, curb and sidewalk repairs on Harris Avenue from Bradley Avenue to Maple Street. A few items (punch list) of work will remain. Lawn restoration will be done by September 30.

Research Road
Duce Construction continues to work on the pavement replacement on Research Road. Duce is nearing completion of phase two and is beginning work on phase three. There are six phases of work total. Due to multiple utility conflicts at the intersection of Research Road, Newton Drive and Newmark Drive, the progress of work has been delayed by at least one week. The original completion date for Research Road is September 30.