Bradley Avenue Lane Closure (between Mattis Avenue and Garden Hills Drive)

In order to perform storm sewer lining, Visu-Sewer of Missouri, LLC, will be closing one westbound lane of Bradley Avenue between Mattis Avenue and Garden Hills Drive. During this time, westbound traffic on Bradley Avenue will be merged into a single lane through a short construction work zone.

Work is scheduled to begin mid-morning on Thursday, March 2, 2023, and is planned to be completed and reopened to traffic by 6 p.m. on the same day. Work operations and lane impacts are daytime only, affecting travel between the hours of 9 a.m. and 6 p.m. Minor traffic delays may occur at work zones. The work is weather dependent and may be delayed in the event of inclement weather.