Sixth Street Road Closures (Between Green and John) – REVISED Dates

In order to complete a series of foundation concrete pours and to erect a tower crane at 708 S. Sixth Street, Core Spaces and J H Findorff will be closing Sixth Street between Green Street and John Street. These closures will occur intermittently during the months of March, April, and May as construction progresses. The City will provide notification for each scheduled closure.

The following closures have been scheduled (Please note that these dates have changed from previous notice):

– Friday, March 15, 2019: Sixth Street will be closed between the hours of 7 a.m. and 5 p.m.

– Tuesday, March 19, 2019 – Friday, March 22, 2019: Sixth Street will remain closed all days and overnights as a tower crane is erected and various concrete pours are completed.

During each closure, Sixth Street will be closed to through traffic between Green Street and John Street.

Sixth Street between Green and John