The State of Illinois awarded a contract to Feutz Contractors to complete Olympian Drive from Legacy Dr to Duncan Road.  Construction began on June 22 and will be completed by the end of October 2015.  Feutz is currently working on removing topsoil from the project area.  The weather has not been cooperating with the construction operation.  Since beginning construction, Feutz has been able to work four days.  When construction begins on Duncan, traffic will be detoured along a marked detour route on Mattis Ave.

 