Next week starting July 14, 2014, Cross Construction Company will continue paving work on Anthony Drive from Mattis Ave. to Marketview Dr. Paving work will also get started in the Dobbins Downs neighborhood north of Anthony Drive. All paving should be complete at this location by the end of the week (weather permitting). Remaining work at this location will consist of incidental driveway paving, pavement striping, and general clean-up work.
Milling of the existing asphalt surface and possible paving work will get started on Hagan Street from Bloomington Rd. to Kenyon Rd. and on Kenyon Rd. from Hagan St. to Market St.
Work for this phase of the project is scheduled to be completed August 8, 2014. Restoration work which consists of sodding will done after the warmer month of August.