Items tagged: Fourth Street

MCORE Project 4 Construction Beginning (Wright Street and Armory Avenue)

On Monday, March 4, the Multimodal Corridor Enhancement Project (MCORE) gets underway with Project 4. The first working area/closures are Armory Avenue between Sixth and Fourth, and sidewalk areas along Armory. The full project corridor includes Armory Avenue, (between Fourth Street and Wright Street) and Wright Street (between Armory Avenue and Springfield Avenue). This phase […]


Campus Signals to Change to Four-Way Stops Over Break

Due to decreased vehicle and pedestrian traffic during winter break, several campus traffic signals have been adjusted to act as a four-way stop by continuously flashing red.  The traffic signals were adjusted today, Friday, December 21, 2018.  Normal signal operations will resume Friday, January 11, 2019.  The signals are at the intersections of: • Fourth […]


Fourth Street Lane Closure

In order to construct a new sanitary main under Fourth Street, Mid Illinois Concrete and Broeren Russo will be closing the northbound lane of Fourth Street between White Street and University Avenue.  The closure will begin on Monday, November 12 and will reopen on Friday, November 30. During the closure, northbound traffic will not be […]


White Street Closure (between Fourth and Fifth Streets)

In order to dismantle their crane, Custom Crane will close White Street between Fourth Street and Fifth Street.  The work is scheduled to begin and end on Monday, October 15, weather permitting.  The street will be closed between the hours of 7 a.m. and 4 p.m. Please plan on using alternate routes during this street closure.  The City […]


Kirby Avenue Lane Closures

In order to perform asphalt street repairs, the Public Works Department will close one lane of traffic in each direction on Kirby Avenue between First Street and Fourth Street.  The work will begin on Tuesday, September 11 at 9 a.m. and is planned to be completed by 4 p.m. Please pay close attention to construction signs […]


MCORE Project Update – Project 2 (Green St. – Third St. to Fourth St.)

MCORE Project Update – Project 2 (Green St. – Third St. to Fourth St.) The City of Champaign and its contractor, Duce Construction, continue to make progress on Project 2 as previously stated in an August 13 press release, however there is one update: The reopening of Green Street between Third Street and Fourth Street […]


Clark Street Road Closure

Clark Street Road Closure In order to safely perform crane operations to erect steel beams, framing, and facade for the new building at 202 S. Fourth Street, Broeren Russo Builders, Inc. will close Clark Street between Fourth Street and Fifth Street.  The street closure will begin on Sunday, July 1, 2018 and will end on Friday, […]


Fourth Street Lane Closure

Fourth Street Lane Closure In order to repair undermined pavement at the corner of Fourth Street and Chalmers Street, Ameren Illinois and Shaw Brothers Concrete have closed the northbound lane of Fourth Street between Armory Avenue and Chalmers Street. The lane closure began on Monday, May 21 and will reopen on Friday, May 25. Northbound […]


MCORE PROJECT CONSTRUCTION WORK TO EXPAND LOCATIONS

MCORE Project Construction Work To Expand Locations On Monday, May 14, the following locations will be added to construction activities related to the MCORE Project: • Green Street between Third Street and Fourth Street. Green Street will be CLOSED, including the intersection of Third Street & Green Street. Green Street will remain closed at this […]


Fourth Street Road Closure

FOURTH STREET ROAD CLOSURE In order to connect utilities at 901 S. Fourth Street, Wick Concrete and Sub 4 Development will close Fourth Street between Daniel Street and Chalmers Street.  The road closure will begin on Monday, March 19  and will reopen on Sunday, March 25.  During the closure, access to local properties will be maintained, but […]