Phase 2 West Washington Street Drainage Improvements (Street Closures on Columbia Avenue and Miller Avenue)

Street closures are planned as part of Phase 2 of the West Washington Street Drainage Improvements Project.  Columbia Avenue and Miller Avenue will be closed in order to install storm sewers and other utilities, more specifically:
• Columbia Avenue will be closed from Carson Avenue to Draper Avenue.
• Miller Avenue will be closed from Church Street to Washington Street.
The street closures listed above are planned to begin on Monday, May 14 and are planned for completion at the end of June, depending on weather.  The streets will be closed to all traffic for the entire planned duration, including the overnight hours.
The City appreciates the cooperation of travelers in the area and encourages caution when travelling in proximity to this work zone.