Healey Street Construction Update

Last week, A&R Mechanical Services, Inc. finished reconstructing the intersection of Healey St. & Sixth St., and the intersection was fully opened to traffic.   By the end of this week, A&R will complete the reconstruction of Healey St. between Fifth St. and Sixth St. On Wednesday, June 25, A&R closed the intersection of Healey St. & Fifth St. to begin work in the intersection. They anticipate completing construction in the intersection and opening it to traffic by Friday, July 11. A&R is currently on schedule to be substantially complete with the entire project by August 15, 2014.