2012 Sewer Lining Project

This project was awarded at the September 18 City Council meeting and consists of rehabilitating sanitary and storm sewers located throughout the City. It includes lining a total of approximately 12,800 lineal feet of sanitary sanitary sewer and 900 lineal feet of storm sewer. SAK Construction from O’Fallon, Missouri, is the contractor for the project at a total a cost of $583,349.

No work was in progress during the past week. If weather permits work throughout the winter, completion of the project is expected by the end of March 2013.