2012 Concrete Street Maintenance

Plymouth Drive
Duce Construction has completed all of the pavement, curb and sidewalk repairs on Plymouth Drive from Harrington Drive to Devonshire Drive. A few items (punch list) of work remain. Lawn restoration will be done in September.

Harris Avenue
Duce Construction will complete all of the pavement patching, curb and sidewalk repairs on Harris Avenue from Bradley Avenue to Maple Street by Friday August 10. A few items (punch list) of work will remain. Lawn restoration will be done in September.

Research Road
Duce Construction began work on pavement replacement on Research Road Wednesday, July 25. Due to multiple utility conflicts at the intersection of Research Road, Newton Drive and Newmark Drive, the progress of work was delayed by one week. The original completion date for Research Road is September 30.