Kirby Avenue / I-57 Overpass Update

IDOT’s contractor, O’Neil Brothers, is approximately 35% complete with the bridge rehabilitation work. O’Neil Brothers has been removing concrete from the south parapet wall and has started removing full depth concrete in preparation of deck patching. O’Neil is on schedule to meet the contract completion date of August 3, 2012. The contract price for this project is $409,252.